Demo - Using Phases to Organize a Project File

Contact Us or call 1-877-932-8228
Demo - Using Phases to Organize a Project File

Demo - Using Phases to Organize a Project File

  1. Open Microsoft Project. Open the file if it is closed.
  2. Select Task #1, Click on Task > Insert > Summary.
  3. Using the steps above, edit the following list of tasks, durations, and predecessors per list below.
    Possible tasks for the project.
    Task Name Duration Predecessors
    Pre-Project Phase
    Client Needs Meeting 1 day
    Create Scope Statement 3 days 2
    Create the list of team assets 2 days 3
    Design Production
    Design Research 3 days 4
    Create a set of design Mock-ups 2 wks 6
    Start Client Iteration Process 3 wks 7
    Slice the design 3 days 8
    Functionality Production
    Functionality Research 3 days 9
    Build the Data Map 2 days 11
    Send the data map to database Developer for Database creation 2 wks 12
    Send Data Map and expectations to .net programmers 1 day 13
    Combine the layout and functionality 1 wk 14
    Host Environment
    Research the host environment 1 day 15
    Establish the host environment 2 days 17
    Upload and test the site 2 days 18
    Confirm Functionality with client 1 day 19
    Alter any issues 1 wk 20
    Go Live! 0 days 21
  4. Save and close the file.