Marking a Project Plan Complete and Storing the Original Files - Exercise

Contact Us or call 1-877-932-8228
Marking a Project Plan Complete and Storing the Original Files - Exercise

Marking a Project Plan Complete and Storing the Original Files

Duration: 15 to 25 minutes.

In this exercise, you will mark the project plan complete and store copies of the original files that would be needed to update or alter the design and functionality.

  1. Open the project plan analysis/Exercises/ProjectPlan_ABC.mpp, mark all items as complete as planned with the exception of the task #6 which took 5 days.
  2. Make a folder in the analysis/Solutions/ folder to house all of your original .PSD art files as well as copies of the .CSS and .HTML files used to build the design..

Solution:

  1. Open the project plan analysis/Exercises/ProjectPlan_ABC.mpp.
  2. Select Task #6 Design Research.
  3. Using the Task> Schedule > Mark on Track > Update Tasks.Update Tasks Section
  4. Update the form to show 100% complete, 5 day duration, and an actual start date of 4/30/2013 with a finish date of 5/6/2013. Click OK.Update Tasks Dialog Box
  5. Select the rest of the tasks and mark them complete as scheduled. Use the 100% icon ( Task> Schedule > 100% Complete).Task Schedule 100 Percent Complete
  6. Save and close the project file.
  7. Make a folder in the analysis/Solutions/ to house all of your original .PSD art files as well as copies of the .CSS and .HTML files used to build the design.Folder Creation