Demo: Update a Project Plan

Contact Us or call 1-877-932-8228
Demo: Update a Project Plan

Demo: Update a Project Plan

  1. Open the project plan analysis/Demos/LovelyLacePlanWphases.mpp.
  2. Select Task #6 Design Research.
  3. Using Task> Schedule > Mark on Track > Update Tasks, establish that the task took a bit longer that we had estimated.
  4. Update the form to show 100% complete, 5 day duration, and an actual start date of 4/26/2013 with a finish date of 5/2/2013. Click OK.
  5. Select the rest of the tasks and mark them complete as scheduled. Use the 100% icon ( Task> Schedule > 100% Complete).
  6. Save and close the project file.
Next